Vinaincon

Vinh Tan 4 Thermal Power Plant Project - Lifting main beam for Boiler of Unit 1
Posted Date: 06.17.2015

2x600 MW Vinh Tan 4 Thermal Power Plant (TPP), package 4 commenced on 9thMarch, 2013. The project has been built in form of EPC Contract (Engineering, Procurement and Construction) and was officially signed on 23rd December, 2013, with Consortium of Doosan Heavy Industries & Construction (DHI, Korea), Mitsubishi Corporation (MC, Japan), Pacific Corporation (PAC, Vietnam) and Power Engineering Consulting Joint Stock Company 2 (EVNPECC2, Vietnam).

The total investment cost of 2x600 MW Vinh Tan 4 TPP is 36,728.640 billion VND. The EPC Contract Price is 1.36 billion USD, in which 85% is funded by KEXIM and KSURE from Korea and JBIC from Japan. The rest, 15%, is the Owner’s fund.

Vinh Tan 4 TPP was committed to completion as ready for being taken over in accordance with the timeframe of 46 months for Unit 1 (at the end of 4th Quarter in 2017) of 52 months for Unit 2 (at the end of the 2nd Quarter in 2018).

Vinh Tan 4 TPP is the conventional steam thermal power, with super critical steam parameters, firing Bituminous/Sub-Bituminous coal imported from Indonesia and Australia. This technology is applied popularly in the World. The power plant is applied modern technology, high capacity and efficiency, with suitable cost. It also ensures environmental requirements according to National and International standards.

When put in operation, Vinh Tan 4 TPP shall firmly enhance the ability in power supply for socio - economic development of South Central region and drastically reduce the dependence on hydro power, especially in dry season. Moreover, it also reduces the quantity of power transmission from North to South and power loss, increase the safety and stability in power operation.

VINAINCON has been executing 2 packages: "Plumbing Work" and "CBB Building and other Works" (See the photos):